Production Schedule for Distant Narratives

preliminary production timeline

10 weeks to complete

week 1 (2.23)

get parts

week 2 (3.2)

create enclosure / box for pc/projector with connections

to underlying camera and ir sensor (arduino)

week 3 (3.9)

continue from week 2

start creating floor surface / rug

week 4 (3.16)

continue from 3 Рbox should be completed  / rug should be close

week 5 (3.23)

rug finished and tested w/ system

(create box for remote)

week 6 (3.30)

continue box for remote

week 7 (4.6)

test complete system, main box, remote box, and rug

week 8 (4.13)

update / repair / revise depending on where things are at

week 9 (4.20)

test system / deploy / document

week 10 (4.27)

built in extra time for any troubleshooting / revising misc.